B. A waste discharge must meet standards and obtain | | authorization if required pursuant to section 413. |
|
| | | Sec. 13. 38 MRSA §490-Z, sub-§12, as enacted by PL 1995, c. 700, §35, | | is amended to read: |
|
| | | 12. Dust. Dust generated by activities at a quarry, | | including dust associated with traffic to and from a quarry, must | | be controlled by sweeping, paving, watering or other best | | management practices for control of fugitive emissions. Dust | | control methods may include calcium chloride as long as the | | manufacturer's labeling guidelines are followed. The department | | may not grant a variance from the provisions of this subsection. | | Visible emissions from a fugitive emission source may not exceed | | an opacity of 20% for more than 5 minutes in any one-hour period. |
|
| | | Sec. 14. 38 MRSA §490-Z, sub-§14, ¶F, as enacted by PL 1995, c. 700, | | §35, is amended to read: |
|
| | | F. A preblast survey is required for all production | blasting and must extend a minimum radius of 2000 feet 1/2 | | mile from the blast site. The preblast survey must document | | any preexisting damage to structures and buildings and any | | other physical features within the survey radius that could | | reasonably be affected by blasting. Assessment of features | | such as pipes, cables, transmission lines and wells and | | other water supply systems must be limited to surface | | conditions and other readily available data, such as well | | yield and water quality. The preblast survey must be | | conducted prior to the initiation of blasting at the | | operation. The owner or operator shall retain a copy of all | | preblast surveys for at least one year from the date of the | | last blast on the development site. |
|
| | | (1) The owner or operator is not required to conduct a | | preblast survey if the department determines that no | | protected natural resource within the limits of the | | otherwise required survey is likely to be affected by | | blasting and production blasting will not occur within | | 2000 feet of any building not owned or under the | | control of the developer. |
|
| | | (2) The owner or operator is not required to conduct a | | preblast survey on properties for which the owner or | | operator documents the rejection of an offer by | | registered letter, return receipt requested, to conduct | | a preblast survey. Any person owning a building within | | a preblast survey radius may voluntarily waive the | | right to a survey. |
|
|