| 3.__Compliance deadline.__The owner or operator of a |
| resource recovery facility with a combustor with a design |
| capacity of less than 350 tons per day but not less than 100 |
| tons per day, in operation as of January 1, 2003, shall submit |
| the application and plan required by subsection 2 within 3 |
| months after the effective date of this section and shall |
| complete installation and begin operation of the necessary |
| emission control equipment as expeditiously as possible, but |
| not later than 18 months after receipt of all required state |
| and local permits and approvals.__The owner or operator of any |
| such combustor shall demonstrate compliance with the emission |
| limits in subsection 1, no later than 21 months after receipt |
| of all required state and local licenses. |