| 2.__Retainage.__In a contract awarded for a public |
| improvement, the public owner may retain 5% of the money due |
| the contractor until substantial completion of the work.__At |
| substantial completion, the owner and the contractor shall |
| inspect the work and prepare a punch list.__The owner may, |
| after inspection of the work, withhold for defective or |
| incomplete work only those funds that are sufficient to |
| account for 1.5 times the value of punch list work.__As punch |
| list work is completed, the retainage held by the owner must |
| be correspondingly reduced.__Funds may not be retained in |
| anticipation of warranty claims but may be retained as |
| directed by the contractor's surety or as necessary to account |
| for liquidated damages or other contract defaults as |
| determined by the designer. |