Title 35-A: PUBLIC UTILITIES
Part 3: ELECTRIC POWER
Chapter 34-D: SOLAR ENERGY DEVELOPMENT DECOMMISSIONING
§3495

§3494. Decommissioning plan

A decommissioning plan must:   [PL 2021, c. 151, §1 (NEW).]
1.  Decommissioning.  Provide for the decommissioning of a solar energy development. For any portion of the development located on land classified as farmland any time within 5 years preceding the start of construction of the development, the plan must provide for the restoration of that farmland upon decommissioning sufficient to support resumption of farming or agricultural activities;  
[PL 2021, c. 151, §1 (NEW).]
2.  Grading and revegetation of earth.  Provide for the grading and revegetation of all earth disturbed during construction and decommissioning, except for areas already restored; and  
[PL 2021, c. 151, §1 (NEW).]
3.  Financial capacity.  Include demonstration of current and future financial capacity, which must be unaffected by the owner's or operator's future financial condition, to fully fund decommissioning in accordance with an approved decommissioning plan under this chapter.  
[PL 2021, c. 151, §1 (NEW).]
SECTION HISTORY
PL 2021, c. 151, §1 (NEW).
The Revisor's Office cannot provide legal advice or interpretation of Maine law to the public.
If you need legal advice, please consult a qualified attorney.
Office of the Revisor of Statutes · 7 State House Station · State House Room 108 · Augusta, Maine 04333-0007
Data for this page extracted on 9/28/2022 08:27:44.
Maine Government
Legislature • Executive • Judicial • Agency Rules
Visit the State House
Tour Guide • Accessibility • Security Screening • Directions & Parking
Email
Office of the Revisor of Statutes