LD 471
pg. 1
LD 471 Title Page An Act to Repeal the Public Utilities Commission's Authority to Issue Certifica... Page 2 of 7
Download Bill Text
LR 617
Item 1

 
Be it enacted by the People of the State of Maine as follows:

 
Sec. 1. 35-A MRSA §3132, as amended by PL 1997, c. 710, §6, is
further amended to read:

 
§3132. Construction of generating facilities prohibited without

 
prior order of the commission

 
An electric utility may not construct any generating facility
or transmission line covered by subsection 1, 1-A or 2 or rebuild
or relocate any transmission line as investigated by the
commission under subsection 3 unless the commission has issued a
certificate of public convenience and necessity approving
construction.

 
1. Construction of generating facility. Whenever any
electric utility or utilities proposes propose to erect within
this State a permanently installed generating facility of more
than 1,000 kilowatts or any transmission line capable of
operating at 100 kilovolts or more, the construction of which is
required to carry the capacity or energy produced by the
generating facility, the following provisions apply.

 
A. The utility or utilities shall file with the commission,
no less than 3 months in advance of submitting its petition
for approval of the proposed facility or lines, a notice of
its intent to file the petition.

 
The notice of intent to file shall must inform the
commission of the location, size, type of facility,
estimated cost and proposed construction schedule of the
generating facility or lines, together with such other facts
and details concerning the proposed facility or lines as the
commission by rule prescribes.

 
B. The petition for approval of the proposed generating
facility or lines shall must contain such information as the
commission by rule prescribes.

 
C. The petition for approval shall must be set down for
public hearing.

 
D. The commission shall issue its order within 15 months after
the petition is filed with the commission unless the period is
either extended by agreement of all the parties or by the
commission upon its determination that the party seeking the
extension would, because of circumstances beyond that party's
control for which it has no reasonable substitute, be
unreasonably disadvantaged unless the


LD 471 Title Page Top of Page Page 2 of 7